NAGUs (Notice Advisory to Galileo Users)

NAGU Definition

The Notice Advisory to Galileo Users (NAGU) aims to inform about any activity/event in the Galileo system with impact on the Signal in Space (SiS) and/or on the performance levels for Open Service (OS), High Accuracy Service (HAS) and Open Service Navigation Message Authentication (OSNMA) as committed in the applicable Open Service-Service Definition Document, HAS Service Definition Document and OSNMA Service Definition Document respectively.

NAGU Categories

  • Planned: all activities/events that have been scheduled and that could potentially have an impact on the service and/or the performance levels. Planned NAGUs aim to inform users about the activity/event with a reasonable advance notice, ahead of their occurrence.
  • Unplanned: all activities/events that have an impact on the service and/or the performance levels that have not been scheduled and could not be foreseen in advance, before their occurrence. The aim of unplanned NAGUs is to inform users about the activity/event within a reasonable time, after their occurrence.

     

NAGU Types and Format

There are different NAGU types defined within each NAGU category:

 

Graphical summary of the OS NAGU types

Graphical summary of the HAS NAGU types

Graphical summary of the OSNMA NAGU types

 

The following table explains the NAGU types currently in use:

 

NAGU TypeNAGU Type (abbreviation)NAGU DescriptionNAGU Format

PLANNED MANOEUVRE

PLN_MANV

Planned activity affecting the attitude and/or orbit (e.g. Station Keeping Manoeuvre, satellite relocation to a new slot).


The planned outage start and end times due to manoeuvre operation are indicated.

Template

PLANNED OUTAGE

PLN_OUTAGE

Planned activity (related to the space and/or the ground segment) that potentially causes an outage of the satellite broadcast SIS (e.g.: on‑board Clock switch, as foreseen by manufacturer for regular equipment maintenance).


The planned outage start and end times are indicated.

Template

CANCELLATION

CANCEL

Cancellation of published NAGU (e.g. due to the withdrawal of planned manoeuvre)

Template

RESCHEDULE

RESCH

Provision of new start/end times for an already published NAGU of “PLANNED” category.

Template

EXTENSION

EXTNS

Provision of a new end time for any already published NAGU of “PLANNED” category, or notification of the planned outage end time for the published NAGU of “UNPLANNED” category: UNP_UNUFN.

Template

SATELLITE DECOMMISSIONED

DECOMMSNG

Commencement of decommissioning phase. 


The end time for the nominal provision of service will be specified.

Template

START OF THE EXTENDED OPERATION MODE

EOM_START

Start time of the Galileo Extended Operation Mode is communicated through this NAGU.

Template

END OF THE EXTENDED OPERATION MODE

EOM_END

Upon recovery of the nominal operation mode, this NAGU is issued to communicate the end time of the Galileo Extended Operation Mode.

Template

UNAVAILABLE UNTIL FURTHER NOTICE

UNP_UNUFN

 

Unscheduled outage of the broadcast satellite Signal in Space, characterised by an undefined duration.

Template

SHORT TERM OUTAGE RECOVERED

UNP_SHTRCVR

Outage events that have been already recovered, before a dedicated NAGU could be published to notify their occurrence.

Template

SATELLITE FIRST TIME USABLE

USABINIT

Announces that a given satellite enters its active service provision, contributing to the constellation service delivery. 


It is used for satellites that enter their service provision for the first time, indicating that the space vehicle is providing a Signal In Space in line with the applicable OS-SIS-ICD, as well as the published OS-SDD and the related service performance commitment.


The type of clock being used to drive the navigation payload is also indicated. 

Template

USABLE FOR SERVICE PROVISION

USABLE

The satellite restarts transmitting healthy Signal in Space, concluding a planned outage period or the recovery after an unplanned outage.
It includes also a reminder about the exact outage start time, along with the precise outage end time.
It includes also the type of clock being used to drive the navigation payload.
This NAGU type is also used following Service Declaration, in order to recall the list of space vehicles that are expected to broadcast a Signal in Space aligned with the applicable OS SDD during the specified service provision phase.

Template

GENERAL NOTICE FOR UNPLANNED EVENTS

GENERAL (NOTICE)

This NAGU type provides general notifications announcing unplanned events such as “Service accuracy degradations”. 
 

Template

GENERAL NOTICE FOR PLANNED EVENTS

GENERAL (NOTICE)

This NAGU type provides general notifications announcing planned events such as “Galileo Initial Open Service (OS) declaration”, “System evolution activity”.
 

Template

LAUNCH

LAUNCH

This NAGU provides notification of Galileo satellite(s) launch event.

Template

 

LEAP SECOND

LEAP SECOND

This NAGU provides notification of a leap second adjustment affecting UTC time scale, following the related announcement by IERS.

Template

PLANNED OUTAGE TIMING SERVICES

TIMING PLN_OUTAGE (GGTO, GST-UTC)

This NAGU provides notification of a planned operation entailing a maintenance of timing related services (GGTO, GST-UTC).

Template

AVAILABILITY OF THE GST-UTC TIMING SERVICE

TIMING USABLE (GST-UTC)

Notification of availability of the GST-UTC timing service following the end of a planned operation / recovery of an unplanned timing outage.

Template

AVAILABILITY OF THE GGTO TIMING SERVICE

TIMING USABLE (GGTO)

Notification of availability of the GGTO timing service following the end of a planned operation / recovery of an unplanned timing outage.

Template

CANCELLATION OF PLANNED OUTAGE TIMING SERVICES

TIMING  CANCEL

Cancellation of a published NAGU notification addressing a planned operation entailing an outage only affecting the timing services (GGTO, GST-UTC).

Template

RESCHEDULE OF PLANNED OUTAGE TIMING SERVICES

TIMING  RESCH

Provision of new start/end times for published NAGU addressing  a planned operation entailing an outage only affecting the timing services (GGTO, GST-UTC).

Template

EXTENSION OF PLANNED OUTAGE TIMING SERVICES

TIMING  EXTNS

Provision of new end time for a published, PLANNED NAGU entailing an outage only affecting the timing services (GGTO, GST-UTC)
 

Template

UNPLANNED OUTAGE GST-UTC TIMING SERVICE

TIMING UNP_UNUFN (GST-UTC)

Unplanned GST-UTC timing service outage.

Template

UNPLANNED OUTAGE GGTO TIMING SERVICE

TIMING UNP_UNUFN (GGTO)

Unplanned GGTO timing service outage.

Template

SHORT TERM OUTAGE GST-UTC TIMING SERVICE

TIMING UNP_SHTRCVR (GST-UTC)

Communication of the recovery of short-term GST-UTC timing service outage.

Template

SHORT TERM OUTAGE GGTO TIMING SERVICE

TIMING UNP_SHTRCVR (GGTO)

Communication of the recovery of short-term GGTO timing service outage.

Template

HAS GENERAL NOTICE FOR PLANNED/UNPLANNED EVENTS

HAS GENERAL (NOTICE)

This NAGU type provides general notifications about general HAS events, e.g., announcement of “HAS Enhanced Service declaration”, “HAS service degradations”, etc.
Depending on the nature of the general event, it will be communicated either before or after its occurrence.

Template

PLANNED OUTAGE HAS SERVICES

HAS PLN_OUTAGE

This NAGU provides
notification of a planned operation entailing an outage of the High Accuracy Service. 

A HAS outage  consists of the complete absence of valid HAS orbit and/or clock corrections for all satellites in the HAS SIS (C/NAV message).

Template

AVAILABILITY OF HAS

HAS USABLE

This NAGU provides
notification of availability of High Accuracy Service following the end of a planned operation / recovery of an unplanned outage, with an impact related to High Accuracy Service.

Template

CANCELLATION OF PLANNED OUTAGE HAS

HAS CANCEL

Cancellation of a published NAGU notification for a planned operation, entailing an outage affecting the High Accuracy Service.

Template

RESCHEDULE OF PLANNED OUTAGE HAS

HAS RESCH

Provision of new start/end times for a published NAGU notification for a planned operation, entailing an outage affecting the High Accuracy Service.
 

Template

EXTENSION OF PLANNED OUTAGE HAS

HAS EXTNS

Provision of new end time for a published,  planned NAGU entailing an outage affecting the High Accuracy Service. 

Template

UNPLANNED OUTAGE HAS

HAS UNP_UNUFN

This NAGU provides
notification of an unplanned outage related with the High Accuracy Service.

Template

SHORT TERM OUTAGE HAS

HAS UNP_SHTRCVR

This NAGU provides
notification of a short term High Accuracy Service outage that has been recovered, before a NAGU could be published. 

Template

OSNMA GENERAL NOTICE FOR PLANNED/UNPLANNED EVENTS

OSNMA GENERAL (NOTICE)

This NAGU type provides notifications about general OSNMA events, e.g., announcement of “OSNMA Enhanced Service declaration”, “OSNMA service degradations”, etc.

Depending on the nature of the general event, it will be communicated either before or after its occurrence. 

Template

OSNMA PUBLIC KEY RENEWAL

OSNMA PK_RENEWAL

An OSNMA Public Key renewal will take place.

Template

OSNMA TESLA CHAIN RENEWAL

OSNMA TESLA_CHAIN_RENEWAL

An OSNMA TESLA Chain renewal will take place.

Template

OSNMA MERKLE TREE RENEWAL

OSNMA MT_RENEWAL

An OSNMA Merkle Tree renewal will take place.

Template

OSNMA PLANNED OUTAGE

OSNMA PLN_OUTAGE

A planned operation affecting the OSNMA service provision will take place.

Template

OSNMA PUBLIC KEY REVOCATION

OSNMA PK_REVOCATION

An OSNMA Public Key revocation took place.

Template

OSNMA TESLA CHAIN REVOCATION

OSNMA TESLA_CHAIN_REVOCATION

An OSNMA TESLA Chain revocation took place.

Template

OSNMA ALERT MESSAGE

OSNMA ALERT_MESSAGE

OSNMA Alert Message was broadcast.

Template

OSNMA UNPLANNED OUTAGE UNTIL FURTHER NOTICE

OSNMA UNP_UNUFN

An unplanned outage affecting the OSNMA service provision took place.

Template

OSNMA UNPLANNED SHORT RECOVERY

OSNMA UNP_SHTRCVR

An unplanned event, that caused an OSNMA outage, that has been already recovered before a dedicated NAGU could be published

Template

OSNMA CANCELLATION

OSNMA CANCEL

Cancellation of published OSNMA NAGU (e.g., due to the withdrawal of a planned outage).

Template

OSNMA RESCHEDULE

OSNMA RESCH

Provision of new start/end times for an already published PLANNED OSNMA NAGU.

Template

OSNMA EXTENSION

OSNMA EXTNS

Provision of a new end time for an already published PLANNED OSNMA NAGU.

Template

OSNMA USABLE

OSNMA USABLE

The OSNMA service is restored after an Alert Message broadcast or a planned/unplanned outage

Template

 

The following table shows the NAGU types that were used in the past (e.g., prior to declaration of OS Initial Services) and are not currently in use:

 

NAGU TypeNAGU Type (abbreviation)NAGU Description

SATELLITE FIRST TIME AVAILABLE

AVAILINIT

Satellite first time available. This NAGU type was used prior to the OS Initial Services Declaration. As of 15th of December, 2016, the OS Initial Services Declaration has taken place and USABINIT NAGU will be published instead of AVAILINIT NAGU.

AVAILABLE FOR TESTING

AVAILABLE

Satellite available for testing purposes. This NAGU type was used prior to the Initial Services Declaration. As of 15th of December, 2016, the OS Initial Services Declaration has taken place and USABLE NAGU will be published instead of AVAILABLE NAGU.

PLANNED UNAVAILABLE UNTIL FURTHER NOTICE

PLN_UNUFN

All planned outages are notified via PLN_OUTAGE. 

SATELLITE UNDER COMMISSIONING

COMMSNG

Superseded by the information provided by the prevision of the scope of the GENERAL NAGU announcing the launch of the satellite.

DEFINITION OF NAGU FIELDS

  1. Header: the first line of the text field includes the title “NOTICE ADVISORY TO GALILEO USERS (NAGU)”, which is followed by the NAGU SPECIFIC number given in the format YYYYNNN, where YYYY is the Gregorian year and NNN is the sequential number of NAGU, starting with 001 on the 1st of January every year and incrementing by 1 at each subsequent NAGU.

  2. Date generated (UTC): the second line contains the date at which the NAGU was generated on the GSC website, in UTC time scale, format YYYY-MM-DD hh:mm where YYYY is the Gregorian year, MM is the number of the month from 1-12 in sequence starting with 1 being January and finishing with 12 being December, DD is the day within the Gregorian month, hh is the hour in the 24 hour format and mm is the minute.

  3. NAGU type: as per NAGU definition. See NAGU types table in the section above.

  4. NAGU number:  this is defined in the format YYYYNNN (previously defined).

  5. NAGU subject: subject of the NAGU summarizing the information provided in the “Event Description”. The text to be used in the subject is defined by the template of each NAGU.

  6. NAGU referenced to: if the current NAGU refers to previous NAGU then the previous NAGU will be in this field in the form of YYYYRRR where YYYY is the Gregorian year the NAGU was issued and RRR is the number of the NAGU for that year. If there is no reference to previous NAGU then “N/A” (not applicable) will appear here instead.

  7. Start date event (UTC): the start date of the event notified in this NAGU in the UTC time scale with format YYYY-MM-DD hh:mm (see the definition of time in “2.” above).

  8. End date event (UTC): the end date of the event notified in this NAGU in UTC time scale with format YYYY-MM-DD hh:mm (see the definition of time in “2.” above).

  9. Satellite affected: GSAT (Galileo SATellite) name of the satellite affected.

  10. Space vehicle ID: SVID of the satellite affected. This field is not present in the GENERAL NAGU.

  11. Signal(s) affected: the signal(s) affected by the satellite referenced in the NAGU. The signals affected will be contained within a bracket after the word SIGNAL and can be one or a combination of the following: E1, E5a, E5b, E6-B, E6-C or ALL. Partial outage/availability of the signals is indicated in the NAGU subject if ALL signals are not affected. This field is not present in the GENERAL NAGU.

  12. Signal(s) affected: the signal(s) affected by the satellite referenced in the NAGU. The signals affected will be contained within a bracket after the word SIGNAL and can be one or a combination of the following: E1, E5a, E5b, E6-B, E6-C, ALL. Partial outage/availability of the signals is indicated in the NAGU subject if ALL signals are not affected.

  13. Event description: the event description following the templates defined for each NAGU.

NAGU Timeliness

The timely publication of NAGUs refers to the time intervals within which Galileo NAGUs are published before any planned event or after any unplanned event. The minimum performance level for the timely publication of NAGUs is specified in the applicable Open Service-Service Definition Document (OS-SDD), High Accuracy Service-Service Definition Document (HAS-SDD), Open Service Navigation Message and Authentication-Service Definition Document (OSNMA-SDD).